Project Report | Nov 17, 2025
Lab Construction Is Progressing Rapidly

By Verna Case | Project Leader

Central corridor view showing doors to side rooms
Central corridor view showing doors to side rooms

Progress on the Mwandi Hospital's new laboratory facility has moved quickly since our last report. Interior walls have been constructed and plastered. Window and door openings are being measured, and installations of these fixtures will follow soon. Electrical wiring is in progress, and the Terrazzo floor team will begin laying the floors in the near future. In addition, a subcontractor recently completed measurements for all laboratory cabinet countertops. These countertops will be prepared off-site and installed after completion of the Terrazzo floors. Most pictures attached to this report were taken during the last week and illustrate the impressive progress that has been made on the building's interiors. The pictures show:

  1. The long corridor running through the building with interior doors to rooms that will house a variety of analytical functions and will improve the hospital staffs abilities to diagnose and treat patients.
  2. An earlier view of the corridor showing progress made on the plastered walls.
  3. A contractor making final measurements in preparation for the installation of windows and doors.
  4. A view toward the corridor from the interior of a lab room being constructed in the building.
  5. An electrician working on wiring for the building.
  6. A recent exterior view of the laboratory building with the added roof.

In summary, significant progress on this new facility has been made since our last report which described the site excavation. If all goes smoothly, the major construction should be completed in January and the finishes (paint, furnishings, etc.) will be completed in time to allow staff to move into the facility in February. The American Partners are grateful, as always, to our donors who have enabled the construction of this up-to-date laboratory facility with Level 2 diagnostic capabilities. We hope to share great pictures of a completed laboratory building in our next report.

Corridor view showing spacious rooms on each side
Corridor view showing spacious rooms on each side
Contractor measuring for window installation
Contractor measuring for window installation
View into corridor from one lab room
View into corridor from one lab room
Electrician at work on wiring
Electrician at work on wiring
Exterior view of building with the added roof
Exterior view of building with the added roof
Share on Twitter Share on Facebook

About Project Reports

Project reports on GlobalGiving are posted directly to globalgiving.org by Project Leaders as they are completed, generally every 3-4 months. To protect the integrity of these documents, GlobalGiving does not alter them; therefore you may find some language or formatting issues.

If you donate to this project or have donated to this project, you can receive an email when this project posts a report. You can also subscribe for reports without donating.

Sign up for updates

Organization Information

UCZ Mwandi Mission Hospital American Partners

Location: Kill Devil Hills, NC - USA
Website:
Project Leader:
first2237518 last2237518
United States

Learn more about GlobalGiving

Teenage Science Students
Vetting +
Due Diligence

Snorkeler
Our
Impact

Woman Holding a Gift Card
Give
Gift Cards

Young Girl with a Bicycle
GlobalGiving
Guarantee

Get incredible stories, promotions, and matching offers in your inbox

WARNING: Javascript is currently disabled or is not available in your browser. GlobalGiving makes extensive use of Javascript and will not function properly with Javascript disabled. Please enable Javascript and refresh this page.